01
The joint
Day joints and panel joints are the drawing. Set them out with the architect at 1:20 and they read as intent rather than as an accident.
Betontechnologie / seit 1996
Mix design, formwork strategy, trial panels and curing. We are the people who say no in week four so nobody has to say it in week forty.

A mix is chosen for colour, workability and bleed before anyone draws a panel layout. Doing it the other way round is how walls come out mottled.
A single delivery source for the whole visible surface. Change the quarry mid-pour and no amount of curing will hide it.
Two panels, cast on site, in the weather the real pour will get. Signed off by the architect before the first real lift.
The wall is decided in the first seven days. We write the curing regime into the contract and inspect it, because nobody else will.


Two panels, full height, cast on the site by the crew who will do the real pour, in whatever weather turns up. Then everybody stands in front of them and agrees, in writing, what acceptable means.
A photograph is not a trial panel. Neither is a sample from another job, another supplier or another season. Concrete is a local material and the panel is the only honest specification.
The signed panel stays on site until practical completion. When a dispute happens, and it does, the wall is compared to the panel and not to anybody’s memory of the panel.

Invisible in the specification, unmissable in daylight, permanent either way.
01
Day joints and panel joints are the drawing. Set them out with the architect at 1:20 and they read as intent rather than as an accident.
02
Rate, vibration and lift height. Most blowholes and most colour variation are decided in the ninety minutes the concrete is moving.
03
Seven days minimum, and the wall is finished in the first three. Strip early and you get a lighter, chalkier surface nobody can fix later.
One example, published because clients ask what a fair-faced specification actually contains.